Halton Roadworks Update

Watkinson Way, Widnes

The works on Watkinson Way will be on-going until April 2019. Traffic Management will be in place until Mid-March.

Resurfacing is due to take place on-

  • Phase 1 - Friday 29th March 19:00 to the 1st April 2019 05:00, weekend overnight closure on Watkinson Way, (Watkinson Way will closed Southbound from Derby Rd, diversion will be in place).
  • Phase 2 – Monday 1st  April 19:00 to 3rd April 2019 05:00, overnight closures for three days, will be open during the day (This affects northbound traffic wanting to Access Fiddlers Ferry Rd and Earle Rd, diversion will be in place).
  • Phase 3 – Friday 3rd April 19:00 to 8th April 05:00 2019, weekend overnight closure on Fiddlers Ferry Rd (Diversion via Earle Rd).
  • Phase 4 – Monday 08th April 19:00 to 10th April 05:00 (Affects all travelling Southbound, diversion will be in place). 

 

Weston Point Expressway, Runcorn

Weston Point Expressway will be closed from Friday 1st March 2019 for about a year.

This for the removal of the trumpet loop, roads connecting the Silver Jubilee Bridge, constructing a roundabout plus demolition of redundant structures. Diversions will be in place via Central Expressway.

 

Halton Borough Council apologies for any inconvenience caused whilst these improvement works are carried out.

 

13th March 2019

« back to news

With thanks to our brand partners
Halton growth hub Astmoor Halebank Dats

© Halton Chamber of Commerce and Enterprise 2014. Registered in England Company Number 3115981.
Halton Chamber of Commerce & Enterprise, 7th Floor, Municipal Building, Kingsway, Widnes, WA8 7QF Terms and Conditions Privacy Policy